FS#15242 — Generators

Attached to Project— Datacenters
Modernization
Roubaix 2
Planned
0%
Following the incident at SBG's site on 9 November, an electrical audit of all our sites was carried out. This was announced in the following work task: http://travaux.ovh.net/?do=details&id=28247 .

Following this audit, we will optimize the electrical design of the RBX-2 emergency power stations to bring them in line with the latest OVH standards.

Part of the planned intervention consists of adding low-voltage generators. This operation will be carried out any loss of power and will have no impact on the continuity of service.

Interventions are scheduled for December 27th from 5am (UTC+1) to 6pm (UTC+1) and on December 28th from 5am (UTC+1) to 6pm (UTC+1).